Nahar Lining Works - Banda District
Nahar LiningCompleted

Nahar Lining Works - Banda District

Banda, Uttar Pradesh

Client

Minor Irrigation Department, Uttar Pradesh

Value

₹ 38 Lakhs

Duration

4 Months

Completed

November 2023

Category

Nahar Lining

Project Overview

This project covered the cement-concrete lining of a 3.2 km nahar network serving agricultural land in Banda district under the Pradhan Mantri Krishi Sinchayee Yojana (PMKSY) scheme. The existing earthen field channels were losing approximately 45% of water to seepage before reaching the fields. Wave Earth Infratech executed the complete lining works including bed and side wall concreting, inlet-outlet structures, and field drain connections - substantially improving irrigation efficiency and reducing water waste across the command area.

Scope of Work

  • Desilting and earthwork shaping of existing nahar: 9,800 cum
  • Cement concrete lining M-15 grade - bed and both side walls
  • Construction of 14 inlet and outlet structures
  • Connecting field drain outlets at farmer field entries
  • Construction of turnout and regulator structures: 4 nos
  • Finishing, curing, and quality testing of lining works
  • Final measurement and handover documentation

Challenges & Solutions

Challenge

Harvest season restrictions meant work had to stop at certain locations during November

Solution

Work schedule adjusted to progress from two ends simultaneously, completing sections away from standing crops first

Challenge

High water table in low-lying sections caused formwork instability

Solution

Dewatering pumps deployed and formwork base deepened with additional shuttering support

Challenge

Existing nahar alignment had sharp curves requiring special formwork

Solution

Flexible panel formwork fabricated on-site to match curved sections accurately

Project Timeline

Week 1-2

Survey, staking, and mobilisation. Earthwork shaping of first 1.0 km

Week 3-5

Earthwork completion and CC lining of Phase 1 (1.0 km)

Week 6-9

CC lining Phase 2 (1.2 km) and inlet/outlet structure construction

Week 10-13

CC lining Phase 3 (1.0 km) and turnout structures

Week 14-16

Curing completion, field drain connections, final testing and handover

Key Quantities

Nahar Length Lined3.2 KM
Earthwork9,800 CUM
CC Lining (M-15)3.2 KM
Inlet/Outlet Structures14 Nos
Farmers Benefited1,200+
Command Area420 Hectares

Equipment Used

  • JCB Excavator - 1 no
  • Dumper Trucks (7T) - 2 nos
  • Concrete Mixer (0.3 cum) - 2 nos
  • Plate Compactor - 1 no
  • Water Tanker - 1 no
  • Vibrator for concrete - 1 no

Project Impact

  • 3.2 KM of nahar network lined, reducing seepage by approximately 45%
  • 1,200+ farmers now receive consistent end-of-channel water supply
  • 420 hectares of command area brought under reliable irrigation
  • Water distribution equity improved across all farmer outlets
  • Reduced maintenance cost for department due to elimination of earthen channel erosion

Need similar work executed?

Request Quotation

Site Gallery

Nahar Lining Works - Banda District site photo 1
Nahar Lining Works - Banda District site photo 2
Nahar Lining Works - Banda District site photo 3
Nahar Lining Works - Banda District site photo 4
Nahar Lining Works - Banda District site photo 5
Nahar Lining Works - Banda District site photo 6