Irrigation Infrastructure Development - Rewa
Irrigation InfrastructureCompleted

Irrigation Infrastructure Development - Rewa

Rewa, Madhya Pradesh

Client

Water Resources Department, Madhya Pradesh

Value

₹ 95 Lakhs

Duration

7 Months

Completed

June 2023

Category

Irrigation Infrastructure

Project Overview

This project involved the design and construction of a new irrigation distribution network in Rewa district under the MP Water Resources Department. The project covered construction of a primary distribution canal, secondary field channels, check dams, and farm-level water control structures to bring 680 hectares under assured irrigation for the first time. Wave Earth Infratech managed the complete civil execution - from excavation and earthwork to RCC structures and commissioning - across a challenging terrain with mixed soil conditions and seasonal flooding risk.

Scope of Work

  • Primary distribution canal excavation and lining: 5.6 km
  • Secondary field channel network: 8.4 km earthen and lined
  • RCC check structures (falls) construction: 12 nos
  • Farm water control outlets: 340 nos
  • Head regulator and sluice gate structures: 3 nos
  • Earthwork excavation and embankment: 42,000 cum
  • Access tracks and maintenance roads: 3.8 km
  • Final commissioning, flow calibration and handover

Challenges & Solutions

Challenge

Mixed soil profile including expansive black cotton soil in eastern sections

Solution

Soil stabilisation with lime treatment before compaction in black cotton sections; additional lining thickness specified

Challenge

Seasonal flooding risk in low-lying areas during kharif season

Solution

Work sequenced to complete flood-prone sections before monsoon onset; temporary flood protection bunds erected

Challenge

Coordination of 340 farm connection points with individual farmers

Solution

Dedicated community liaison team worked with village panchayats to schedule and confirm each farm outlet location

Challenge

RCC check structure foundations encountered hard rock at 1.2m depth

Solution

Rock breaking equipment deployed; foundation design adjusted with department approval

Project Timeline

Month 1

Survey finalisation, setting out, and full mobilisation

Month 2-3

Primary canal excavation and embankment formation: 5.6 km

Month 3-4

RCC check structures and head regulator construction

Month 4-5

Secondary channel network excavation and lining

Month 5-6

Farm outlet connections, access road formation

Month 7

Commissioning, flow testing, final inspection, and handover documentation

Key Quantities

Primary Canal5.6 KM
Secondary Channels8.4 KM
Check Structures12 Nos
Farm Connections340 Nos
Earthwork42,000 CUM
Command Area680 Hectares

Equipment Used

  • Hydraulic Excavator (PC200) - 2 nos
  • JCB Backhoe - 1 no
  • Dumper Trucks (10T) - 5 nos
  • Concrete Batching Equipment - 1 set
  • Concrete Mixers - 4 nos
  • Compactor Rollers - 2 nos
  • Dewatering Pumps - 3 nos
  • Water Tanker - 2 nos

Project Impact

  • 680 hectares brought under assured irrigation for the first time
  • Approximately 1,800 farming families now have access to canal water
  • Estimated 30-35% increase in rabi crop yields projected in command area
  • 12 check structures improve water management and distribution control
  • Reduced dependence on groundwater irrigation in the project area
  • Maintenance road network enables department for year-round access

Need similar work executed?

Request Quotation

Site Gallery

Irrigation Infrastructure Development - Rewa site photo 1
Irrigation Infrastructure Development - Rewa site photo 2
Irrigation Infrastructure Development - Rewa site photo 3
Irrigation Infrastructure Development - Rewa site photo 4
Irrigation Infrastructure Development - Rewa site photo 5
Irrigation Infrastructure Development - Rewa site photo 6