Large-Scale Earthwork & Embankment - Panna
Panna, Madhya Pradesh
Client
PWD (Public Works Department), Madhya Pradesh
Value
₹ 74 Lakhs
Duration
6 Months
Completed
September 2022
Category
Earthwork & Excavation
Project Overview
This project involved large-scale bulk earthwork, cut and fill operations, and compacted embankment formation for a 9.2 km road alignment in Panna district under the PWD MP. The project required significant terrain reshaping, including rock cutting in elevated sections and fill embankment in valley crossings. Wave Earth Infratech deployed a fleet of heavy excavation and earth-moving machinery to complete the earthwork within the contracted timeline, maintaining specified compaction densities across all embankment sections.
Scope of Work
- Site clearing and grubbing across 9.2 km alignment
- Rock cutting and hard excavation: 12,400 cum
- Soil excavation and cut fill: 55,600 cum
- Compacted embankment formation to specified density
- Subgrade preparation and trimming to formation level
- Box culvert construction (RCC): 8 nos
- Slope protection and stone pitching at critical embankment sections
- Drainage channels and cross-drainage works
Challenges & Solutions
Challenge
Unexpectedly hard basalt rock encountered in the elevated sections beyond initial estimates
Solution
Rock breaker attachment deployed on excavator; additional time factored in; final measurement revised with department approval
Challenge
Sandy fill material in valley sections failing compaction density tests
Solution
Borrow material replaced with approved laterite-soil mix; compaction process adjusted with additional passes
Challenge
Heavy rains during July-August disrupted embankment compaction work
Solution
Work rescheduled to night hours and early morning when ground was workable; polythene sheeting used to protect completed layers
Project Timeline
Month 1
Site clearing, staking, temporary access, and mobilisation of all machinery
Month 2
Rock cutting in hill sections (Ch. 0-2.5 km) and bulk excavation
Month 3
Cut and fill operations Ch. 2.5-5.5 km; embankment layer compaction
Month 4
Embankment Ch. 5.5-7.8 km; culvert construction at 4 locations
Month 5
Embankment Ch. 7.8-9.2 km; remaining 4 culverts; slope protection
Month 6
Subgrade trimming, drainage channels, quality testing, and final handover
Key Quantities
Equipment Used
- Hydraulic Excavator (PC300) - 3 nos
- JCB Backhoe Loader - 2 nos
- Dumper Trucks (12T) - 6 nos
- Vibratory Roller (10T) - 2 nos
- Motor Grader - 1 no
- Rock Breaker Attachment - 1 no
- Concrete Mixer - 2 nos
- Water Tanker - 1 no
Project Impact
- 9.2 KM of road alignment earthwork completed to PWD specification
- All 8 culverts constructed to design specification and load-bearing standard
- Project completed within contracted timeline despite weather delays
- All embankment sections passed compaction density tests at first inspection
- Improved all-weather road access for 4 villages previously cut off in monsoon